What to expect next week:
Finished Rough Animation (I only have 4 scenes left, and 2 of those are already nearly complete. One shot I haven't started yet, but is very simple. The last shot I need roughed is my 16 second scene. Most of this week is going to be dedicated to just that.)
2 More Clean Scenes
How's my progress?
Pretty great! I was able to get from behind schedule, to ahead of schedule in the span of a week which felt nice.
After this new approach to my schedule I was able to accomplish nearly DOUBLE my output from the past two weeks combined in just one week.
If all goes according to plan, I'm on pace to finish animation (including inking/clean-up) on this film two weeks early.
Concerns?
That 16 second scene. That's going to be a huge pain in my side, and I need to get it done this week so my composer and my sound designer can start working. I believe I can do it with my current schedule, but that scene may end up being ""rougher"" than usual.